Tonbridge Power Inc. Website

What to Expect

Each landowner can expect a sequence of events leading up to and during construction on their property that will roughly unfold as follows:

Landowner Agreement

The first step in preparation for construction will be to reach an agreement with each landowner on how the transmission line can traverse the property and what compensation is appropriate for that right. In arriving at that agreement, a landowner can expect to speak with one or more of the following:

Back To Top

Construction Agreement/Land Form

Before the contractors can commence their work, discussions will take place between MATL and the landowners about where, when and how the right of way may be used during construction. These discussions will cover the sequence of events that will take place during the construction process, any impositions this will place on the property and farming operations, and the measures that need to be taken to keep the landowner financially whole. This will be documented, clearly identifying the landowner’s rights and MATL’s obligations, including:

The fundamental principle underlying any agreement reached with a landowner, in relation to construction access, is that the property will be returned to its original condition when the works are finished (except where this is not possible, in which case, suitable compensation will apply; e.g. crop loss).

Back To Top

The Five (5) Phases of Construction

Construction will be scheduled to minimize impact, particularly on the most environmentally sensitive sites. Each phase of construction will be completed sequentially by specialized crews including: survey, assembly, excavation, erection, clipping and restoration. There may or may not be a continuous presence of construction personnel on the property during this process.

1. Right of Way Review and Preparation

Qualified specialists will perform site-specific inspections including topographical and geotechnical surveys. Topographical surveys establish the shape of the terrain, allowing poles to be placed and sized in such a way that proper safety clearances are maintained. Geotechnical surveys assess the soil type where the poles will be installed. This information is used to determine pole foundation design including to what depth the pole needs to be placed in the earth. Topographical surveys involve little if any impact on the land, but geotechnical surveys do require drilling with equipment and will only be undertaken with the prior consent of the landowner.

The location of poles is staked out in advance. This allows for final input from landowners, a subsurface assessment to locate potential obstructions such as buried gas lines, and the confirmation of surface features and clearances.

Before poles are installed the property will be prepared to allow access by construction vehicles. This may include temporary access-gate and culvert installation, construction of temporary approaches, route grading and the laying of gravel where required. All site preparation work is done in accordance with landowner agreements.

Back To Top

2. Material Procurement and Delivery

Transmission poles will be pre-cut, pre-drilled, and delivered to several staging areas along the route of the transmission line. Pole assemblies will then be hauled to each structure location using tractor trailers or trucks equipped with cranes for unloading.

Back To Top

3. Tower Installation

Wooden H-frame structures or long- or short-span steel monopoles will be erected at their design spacing along the transmission right of way. The installation of each type will be quite similar; an auger truck or similar piece of equipment will excavate the appropriate hole or holes in the ground. An hydraulic crane will then be used to raise the pre-assembled structure vertically and place it in the ground. Backfill will be gravel, a dry gravel and cement mix, or concrete, depending on the foundation design.

In some instances guy wires will be installed. These provide additional support to angle and dead-end structures. They splay out in a pattern around the tower on the opposite side to the force they are designed to counter. This varies depending on the geometry of the transmission system at that location. Guy wires are made of galvanized steel and are fixed to the ground using steel screw-in anchors. Protective barriers may be installed if required.

Back To Top

4. Wire Stringing

The conductor cables that will carry the electricity are installed using specially-designed tension-stringing equipment. Temporary “puller and tensioner” sites will be located four to six kilometers apart along the transmission route. These are used to pull the conductors into the right position for installation. Anchors hold the equipment in place while the conductor is pulled tight. Once the correct tension is achieved, clipping crews remove the stringing blocks used during installation and clamp the conductors in place at the end of the insulators.

Five wires are strung from H-frame structures: three conductors, one overhead ground wire and one optical ground wire (“OPGW” - a combination ground wire and fiber optic bundle, the latter used for system monitoring and protection). An overhead ground wire is not used on monopoles, and so only four wires are strung on these structures.

Typical structure configurations being employed on the MATL line

Back To Top

5. Clean-up and Reclamation

When construction is finished, MATL will return the land to its original condition or compensate the landowner fully where this is not possible; for example, if crops are damaged. This may involve re-grading or re-tilling, removing temporary works and surplus soil, re-seeding, and repairing fences and gates. The degree of reclamation required will vary depending on the season of construction.

Back To Top